9-Lot Minor Subdivision
Description:
The minor subdivision procedure is a process for development and review of subdivisions proposing a maximum of nine (9) lots, excluding those outlots which will not be used for residential, industrial or commercial purposes.
Minor Subdivision Processing Steps & Timeline
- Survey - Topography & Boundary - 21 days
- Sketch Plan - Weld Administrative Review - 60 Days
- Change of Zone - Board of County Commissioners* - 140 Days
- Final Plat - Board of County Commissioners - 90 Days
- Board of County Commissioners
Total: 311 Days
* Approval type depends on outcome of Change of Zone
Weld County Notes:
- Pre-application meeting is necessary for a Minor Subdivision Planning Web Site
- Drainage Report by Civil Engineer Required - in compliance with Section 24-7-110 of the Weld County Code.
- Geotechnical Report by Soils Engineer Required
- Preliminary Traffic Study by Transportation Engineer Required
- Owner must provide Authorized Agent letter for anyone other than owner to sign application and to act on agents behalf.
- Title commitment is required - a Certificate of Conveyance from a title commitment is required. Request this as early in the process as possible.
- Print "Statement of Taxes Due" from Treasurer's Web Site by inserting the account no. (i.e. R5206003)
- Lefthand Water referral letter - fill out application from web site, take to office in Niwot at 6800 Nimbus Rd. with a $25 check and they will get you a letter within a day usually. http://www.lefthandwater.org/Downloads/County_Referral_Review.pdf
Related Links:
- Weld County Subdivision Code
- Minor Subdivision Procedural Guide
- Change of Zone Procedural Guide (COZ)
- Final Plat Procedural Guide
- Weld County Planning & Zoning Web Site
- Land Use Fees
- Lefthand Water Web Site
Post new comment